March 2020
At last work to start after the long delay. Quote for boiler cladding
March 2020
August 2020
Llangollen borrowed our pony truck compensating transverse beam to keep 3802 running.
SEPTEMBER 2020
Asked for progress report - work on 3814 has been severely disrupted this year by Covid 19. Cladding has arrived and will email when work restarts.
SEPTEMBER 2020
NOVEMBER 2020
Opened email with excitement but DEVASTATION - told engineering dept to close and we would have to move again after 2 more wasted years.
DECEMBER 2020
Stressful - 3rd time lucky? Do we have the strength to trust again or do we sell?
DECEMBER 2020
JANUARY 2021
Decision time. Which contractor? Must be able to have capacity to start asap. Northern Steam Engineering Limited had and is local making visits to see progress easy. Transport arranged with Andrew Goodman. Anticipated move end Feb beginning March.
17th FEBRUARY 2021
Good news at last 3814 delivered to Northern Steam Engineering. New beginning.
17th FEBRUARY 2021
14th May 2021
Ordered new tyres for loco from South Devon Railway. Not as cheap as car tyres.
17th JUNE 2021
First invoices from NSEL - preparation for boiler and wheel removal
17th JUNE 2021
22nd JULY 2021
Tender arrived at NSEL. Delivered safely from Llangollen at last. Hope it can be finished in time.